甘肃能化集团金昌公司煤化工项目最重 最高单体设备洗涤塔吊装就位
责任编辑:cnlng    浏览:44次    时间: 2024-07-02 11:06:44    | 来源:甘肃能源化工投资集团   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:6月25日,甘肃能化集团金昌公司煤化工项目最重、最高单体设备——脱硫脱碳装置变换气洗涤塔一次吊装成功,标志着公司项目建设进入新阶段,为后续管道安装施工奠定了坚实基础。据悉,此次吊装的洗涤塔是项目建设的核心设备之一,塔体净重426吨,高95.3米,直径3.4米,..

分享到:

6月25日,甘肃能化集团金昌公司煤化工项目最重、最高单体设备——脱硫脱碳装置变换气洗涤塔一次吊装成功,标志着公司项目建设进入新阶段,为后续管道安装施工奠定了坚实基础。

据悉,此次吊装的洗涤塔是项目建设的核心设备之一,塔体净重426吨,高95.3米,直径3.4米,为确保吊装任务顺利实施,金昌公司同施工单位严格落实各项准备工作,不断优化施工方案,对施工机械设备进行专项检查,并对现场管理人员、施工人员进行了安全技术交底,确保项目施工过程的规范性及安全性。此次吊装采用2000吨履带式起重机主吊、400吨履带式起重机溜尾,通过采用单主机抬吊递送法,成功实现了设备“穿衣戴帽”式的吊装,确保了设备精准就位。

下一步,金昌公司将持续推动项目建设提速提质提效,抢抓项目施工“黄金期”,顺利实现项目年底中交目标。

On June 25, Gansu NENG Hua Group Jinchang Company coal chemical project, the heaviest and highest single equipment - desulfurization and decarbonization device conversion gas scrubber tower was successfully lifted, marking the company's project construction into a new stage, laying a solid foundation for the subsequent pipeline installation and construction.

It is reported that the scrubber is one of the core equipment of the project construction, the net weight of the tower is 426 tons, the height is 95.3 meters, the diameter is 3.4 meters, in order to ensure the smooth implementation of the lifting task, Jinchang company with the construction unit strictly implement the preparatory work, constantly optimize the construction plan, and carry out special inspection of the construction machinery and equipment. And to the site management personnel, construction personnel for safety technology disclosure, to ensure the standardization and safety of the project construction process. The lifting of 2000 tons of crawler crane main crane, 400 tons of crawler crane tail, through the use of a single host lifting delivery method, successfully achieved the equipment "wearing hats" type of lifting, to ensure that the equipment accurately in place.

In the next step, Jinchang Company will continue to promote the project construction speed, quality and efficiency, seize the "golden period" of project construction, and successfully achieve the target of the end of the project.