福能贵电#1机组超低排改造二级吸收塔主体结构封顶
责任编辑:cnlng    浏览:306次    时间: 2024-08-06 13:47:28    | 来源:福能贵州发电有限公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:#1机组超低排放改造脱硫部分是技改主线,而脱硫二级吸收塔是整个脱硫系统改造工程的关键环节。吸收塔总高46.2米,直径17.9米,塔体主要由壁板、顶板、环梁、梯子平台、人孔门、吸收塔接管、吸收塔入口烟道、吸收塔出口烟道等组成。为确保技改项目有序推进,公司领导..

分享到:

#1机组超低排放改造脱硫部分是技改主线,而脱硫二级吸收塔是整个脱硫系统改造工程的关键环节。吸收塔总高46.2米,直径17.9米,塔体主要由壁板、顶板、环梁、梯子平台、人孔门、吸收塔接管、吸收塔入口烟道、吸收塔出口烟道等组成。为确保技改项目有序推进,公司领导提前谋划,精心布置,根据技改项目进度,倒排工作计划,公司领导亲自参与全过程监督管理,大力协调设备方与施工方等。

项目自开工以来,公司抓质量、保安全、抢进度。施工过程中,设备管理部联合参建单位湖南省工业设备安装有限公司,充分发挥团结协作、勇于拼搏的精神,在高温酷暑的工作环境下,始终坚守岗位,严格把控每一个施工环节,保证了工程质量和施工安全。

本次#1号机组脱硫二级吸收塔的封顶,不仅为后续设备安装和调试工作创造了有利条件,也极大地鼓舞了参建人员的士气。福能贵电全体员工将以此次封顶为新的起点,继续保持严谨的工作态度和高效的工作作风,全力推进超低排放改造项目建设,确保#1机组超低排放改造项目按时竣工投产。

The desulfurization part of Unit #1 ultra-low emission transformation is the main line of technical transformation, and the desulfurization secondary absorption tower is the key link of the whole desulfurization system transformation project. The absorption tower has a total height of 46.2 meters and a diameter of 17.9 meters. The tower body is mainly composed of wall panel, top plate, ring beam, ladder platform, manhole door, absorption tower nozzle, absorption tower inlet flue, absorption tower outlet flue, etc. In order to ensure the orderly advancement of the technical transformation project, the company's leaders plan in advance, carefully arrange, according to the progress of the technical transformation project, reverse the work plan, the company's leaders personally participate in the whole process supervision and management, and vigorously coordinate the equipment side and the construction side.

Since the project started, the company has grasped the quality, ensured the safety and hurried the progress. During the construction process, the equipment management Department jointly participated in the construction of Hunan Industrial Equipment Installation Co., LTD., give full play to the spirit of unity, cooperation and courage to struggle, in the high temperature and hot summer working environment, always stick to the post, strictly control every construction link, to ensure the quality of the project and construction safety.

The capping of the desulfurization secondary absorption tower of Unit #1 not only created favorable conditions for the subsequent installation and commissioning of equipment, but also greatly encouraged the morale of the construction personnel. All the staff of Funeng GUI Electric will take this capping as a new starting point, continue to maintain a rigorous work attitude and efficient work style, and fully promote the construction of ultra-low emission transformation projects to ensure that the ultra-low emission transformation project of Unit #1 is completed and put into operation on time.