引绰济辽工程文得根水电站首台机组顺利并网
责任编辑:cnlng    浏览:258次    时间: 2024-06-05 10:18:44    | 来源:内蒙古水务投资集团   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:此举标志着文得根水电站正式进入并网试验阶段,此后将进行系列试验项目,并择机转入72小时试运行阶段。作为国务院确定的“十三五”期间实施的172项节水供水重大水利工程,今后,文得根水电站将把源源不断的清洁能源,送往蒙东地区。文得根水电站总装机容量36兆瓦,拥..

分享到:

此举标志着文得根水电站正式进入并网试验阶段,此后将进行系列试验项目,并择机转入72小时试运行阶段。作为国务院确定的“十三五”期间实施的172项节水供水重大水利工程,今后,文得根水电站将把源源不断的清洁能源,送往蒙东地区。

文得根水电站总装机容量36兆瓦,拥有3台单机容量11.4兆瓦和1台单机容量1.8兆瓦的水轮发电机组,设计额定流量121.64立方米/秒。电站充分利用引绰济辽工程文得根水利枢纽19.64亿立方米库容,年均可发8315万度电,是一座以供水为主,结合灌溉、兼顾发电等综合利用的水利水电工程。

为确保顺利发电,参建各方在面对工期紧、任务重的情况下,提前分析部署,精心组织、合理分工、优化调试方案,制定机组启动试运行方案,克服各类不可预见因素影响,积极组织协调机组调试和系统试运转,相继完成发电机短路试验、空载特性试验、励磁特性试验等各项关键性试验。

This marks the formal entry of the Wendegen hydropower Station into the grid-connected test stage, after which a series of test projects will be carried out, and the opportunity to enter the 72-hour trial operation stage. As the 172 major water-saving and water-supply water conservancy projects implemented during the "13th Five-Year Plan" period determined by The State Council, in the future, the Wendgen Hydropower Station will send a steady stream of clean energy to eastern Mongolia.

The Wendgen Hydropower Station has a total installed capacity of 36 MW, with three hydropower turbines with a capacity of 11.4 MW and one with a capacity of 1.8 MW, with a designed rated flow rate of 121.64 cubic meters per second. The power station makes full use of the 1.964 billion cubic meters of storage capacity of the Wendegen Water Conservancy Project of Yinchuojili Project, and can generate 83.15 million KWH of electricity annually. It is a comprehensive utilization of water conservancy and hydropower project that mainly focuses on water supply, combined with irrigation and power generation.

In order to ensure smooth power generation, in the face of tight construction period and heavy tasks, the participating parties analyze and deploy in advance, carefully organize and rationally divide labor, optimize the commissioning plan, formulate the commissioning plan of the unit, overcome the influence of various unforeseen factors, and actively organize and coordinate the commissioning of the unit and the system trial operation. Complete the generator short circuit test, no-load characteristic test, excitation characteristic test and other key tests successively.