免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!
This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.
电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com
摘要:8月1日,淮北国安电厂二期项目2×660兆瓦超超临界机组主体工程施工项目1号锅炉钢架全面吊装,标志着项目建设迈入了新阶段。为保证此次1号锅炉钢架结构吊装工作顺利进行,项目部成立吊装专项工作组,充分研究并反复论证锅炉钢架结构吊装方案,最终采用120吨塔吊对钢架..
8月1日,淮北国安电厂二期项目2×660兆瓦超超临界机组主体工程施工项目1号锅炉钢架全面吊装,标志着项目建设迈入了新阶段。 为保证此次1号锅炉钢架结构吊装工作顺利进行,项目部成立吊装专项工作组,充分研究并反复论证锅炉钢架结构吊装方案,最终采用120吨塔吊对钢架结构进行吊装。吊装前,项目部组织参与作业的工人进行安全技术交底,对吊装准备、吊装流程、安全措施、质量控制等各方面进行了详细要求。吊装过程中,吊运人员、指挥人员步骤清晰,信号准确,地面施工人员协调一致,配合默契,项目管理人员旁站监督,确保了1号锅炉首根钢架结构顺利就位。下一步,项目部将按照里程碑节点计划,细化分解进度任务,锚定目标,全力推动项目建设“再加速”。 On August 1, the No. 1 boiler steel frame of the main construction project of the 2×660 MW ultra-supercritical unit of Huaibei Guoan Power Plant Phase II was fully lifted, marking a new stage of project construction. In order to ensure the smooth lifting of the steel frame structure of the No. 1 boiler, the project department set up a special lifting working group to fully study and repeatedly demonstrate the lifting plan of the steel frame structure of the boiler, and finally used a 120-ton tower crane to lift the steel frame structure. Before hoisting, the project department organized the workers involved in the operation to disclose the safety technology, and made detailed requirements on various aspects such as hoisting preparation, hoisting process, safety measures and quality control. During the lifting process, the steps of the lifting personnel and the command personnel were clear, the signals were accurate, the ground construction personnel were coordinated and cooperated with each other, and the project management personnel stood by to supervise, ensuring that the first steel frame structure of the No. 1 boiler was successfully in place. In the next step, the project department will, according to the milestone node plan, refine and decompose the schedule tasks, anchor the goals, and fully promote the "re-acceleration" of the project construction. |