中核机械工程成功吊装全球最大海上风机
责任编辑:cnlng    浏览:172次    时间: 2024-09-04 13:17:55    | 来源:中核机械工程有限公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:MySE18.X-20MW机组具有“模块化、轻量化、高效率、高可靠”的特点,其风机叶轮中心高度高,部件吊装重量重,中核机械工程采用3200t履带式起重机进行吊装。该机组不仅适用于国内中高风速、台风地区,还可以应用于欧洲及其它国际高风速区域。同时,其复杂多变的吊装环..

分享到:

MySE18.X-20MW机组具有“模块化、轻量化、高效率、高可靠”的特点,其风机叶轮中心高度高,部件吊装重量重,中核机械工程采用3200t履带式起重机进行吊装。

该机组不仅适用于国内中高风速、台风地区,还可以应用于欧洲及其它国际高风速区域。同时,其复杂多变的吊装环境,也对大风机的运输、吊装等各环节提出了前所未有的挑战。中核机械工程项目团队提前统筹谋划,优化施工组织并开展技术创新,根据风电机组部件结构特性,创造性地针对3200t履带式起重机的结构和作业工况进行了优化升级,有效了保障各部件吊装施工的安全性。在不到一个月的时间内,完成了起重机的进场组装、升级后的性能调试和试验、风机吊装专用工装试验、风机部件吊装与安装等工作,大幅提升了施工效率,再度刷新风电最大试验机组施工的“中核速度”,以最优施工工艺、强大技术保障,响应并满足客户需求,为客户提供“更重、更远、更安全”的专业化服务,竭诚为客户创造价值。

以年平均风速8.5m/s测算,该机组全年发电量可达8000万度,相当于减少二氧化碳排放6.6万吨,约等于9.6万居民的年总用电量。

MySE18.X-20MW全球最大海上风电试验机组安装的圆满完成,是公司在新能源建设业务领域打造具有重要战略意义、行业领先的标杆工程的具体实践,体现了中核机械工程新能源建设先进建造实力,为海上风电项目市场开发奠定了坚实的基础和良好口碑。未来,中核机械工程将持续深入拓展新能源建设市场,为产业换新、新能源产业发展贡献中核吊装力量。

MySE18.X-20MW unit has the characteristics of "modularity, lightweight, high efficiency and high reliability", the central height of the fan impeller is high, the lifting weight of the components is heavy, and the central nuclear mechanical engineering uses 3200t crawler crane for lifting.

The unit is not only suitable for domestic medium and high wind speed, typhoon areas, but also can be applied to Europe and other international high wind speed areas. At the same time, its complex and changeable lifting environment also poses unprecedented challenges to the transportation and hoisting of large fans. CNNC Mechanical engineering project team made overall planning in advance, optimized construction organization and carried out technical innovation, and creatively optimized and upgraded the structure and working conditions of 3200t crawler crane according to the structural characteristics of wind turbine components, effectively ensuring the safety of lifting construction of each component. In less than one month, we completed the approach assembly of the crane, the performance debugging and test after upgrading, the special tool test for fan hoisting, the hoisting and installation of fan components, etc., greatly improved the construction efficiency, once again refreshed the "core speed" of the construction of the largest wind power test unit, and responded to and met the needs of customers with the best construction technology and strong technical support. To provide customers with "heavier, farther, safer" professional services, dedicated to create value for customers.

Based on the annual average wind speed of 8.5m/s, the annual power generation of the unit can reach 80 million KWH, equivalent to reducing carbon dioxide emissions of 66,000 tons, about equal to the total annual electricity consumption of 96,000 residents.

The successful completion of the installation of MySE18.X-20MW, the world's largest offshore wind power test unit, is the company's specific practice in the field of new energy construction business to create an important strategic significance, industry-leading benchmarking project, reflecting the advanced construction strength of CNNC Mechanical engineering new energy construction, for offshore wind power project market development has laid a solid foundation and good reputation. In the future, CNNC Mechanical Engineering will continue to expand the new energy construction market and contribute to the nuclear lifting force for industrial renewal and new energy industry development.