三门核电3号核岛主蒸汽管道首道焊口焊接完成
责任编辑:cnlng    浏览:410次    时间: 2024-08-06 13:39:10    | 来源:中核五公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:主蒸汽管道采用大厚壁合金钢管道材质,对焊接工艺有着特殊要求。开焊前,项目部制定了严密的施工计划,通过线上视频、线下会议多次讨论主蒸汽安装方案、焊接方案、特措方案,对安装逻辑、施工过程采用三维动画进行模拟,并对现场施工组织、人员、设备进行周密部署和..

分享到:

主蒸汽管道采用大厚壁合金钢管道材质,对焊接工艺有着特殊要求。开焊前,项目部制定了严密的施工计划,通过线上视频、线下会议多次讨论主蒸汽安装方案、焊接方案、特措方案,对安装逻辑、施工过程采用三维动画进行模拟,并对现场施工组织、人员、设备进行周密部署和专项交底,全力保证主蒸汽管道焊接顺利完成。同时,为提高施工效率,践行“宜模则模”模块化施工理念,项目部将主蒸汽临时支撑和垂直立管进行集成整体模块化预制安装。

8月份的三门现场酷暑难耐,焊工师傅们热情不减,在“烤”验中实现了三门核电二期工程核岛首道焊口焊接开门红,标志着三门核电二期工程3号机组二回路管道安装工作已全面进入攻坚阶段,为3号机组安全壳顶封头就位里程碑节点实现、厂房内主蒸汽管道安装打下了坚实的基础!

The main steam pipe is made of large thick wall alloy steel pipe material, which has special requirements for welding process. Before the welding started, the project department formulated a strict construction plan, discussed the main steam installation scheme, welding scheme and special plan several times through online videos and offline meetings, simulated the installation logic and construction process using three-dimensional animation, and carefully deployed the on-site construction organization, personnel and equipment and made special information, so as to ensure the smooth completion of the main steam pipeline welding. At the same time, in order to improve the construction efficiency and practice the modular construction concept of "mold is mold", the project department will integrate the main steam temporary support and vertical riser into the overall modular prefabrication installation.

In August, the Sanmen site scorching heat, the enthusiasm of the welder masters did not decrease, in the "baking" test to achieve the Sanmen nuclear power phase II project nuclear island first weld opening, marking the Sanmen nuclear power phase II project No. 3 unit second loop pipeline installation has fully entered the critical stage, It has laid a solid foundation for the realization of the milestone node of the installation of the containment top head of Unit 3 and the installation of the main steam pipeline in the plant!