沙坪一级水电站厂坝工程厂房尾水平台首榀预制梁架设完成
责任编辑:cnlng    浏览:10次    时间: 2024-10-18 10:27:55    | 来源:中国能建葛洲坝一公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:据悉,沙坪一级水电站厂坝工程厂房尾水平台预制梁共计60榀,涵盖了7种形式的T型交通梁,本次成功架设的T型交通梁,长16.52米、梁中高1.3米、顶板宽1.26米,底板宽0.45米、重36.09吨。为确保厂房尾水平台首榀预制梁顺利架设完成,项目部科学制定施工方案,提前召开专..

分享到:

据悉,沙坪一级水电站厂坝工程厂房尾水平台预制梁共计60榀,涵盖了7种形式的T型交通梁,本次成功架设的T型交通梁,长16.52米、梁中高1.3米、顶板宽1.26米,底板宽0.45米、重36.09吨。

为确保厂房尾水平台首榀预制梁顺利架设完成,项目部科学制定施工方案,提前召开专题施工研讨会,组织现场施工班组层层落实技术交底和操作规程,优化机具和人力配置,强化现场施工组织,要求全体参建人员在架设过程中严格遵循操作规程,确保各环节紧密衔接,保证架设施工安全、质量和效率,为厂房尾水平台首榀预制梁的顺利架设提供了有力保障。目前,沙坪一级水电站厂坝工程厂房建设正处于关键冲刺阶段,厂房尾水平台首榀预制梁顺利架设为厂房建设按下了“加速键”。接下来,项目部将继续锚定首台机组发电目标,在确保安全的前提下,全力以赴确保各项工作保质保量完成,向着按期实现首台机组发电目标稳步迈进。

It is reported that a total of 60 prefabricated beams on the tailwater platform of the dam project of Shaping hydropower station, covering 7 forms of T-type traffic beams, the successful erection of T-type traffic beams, 16.52 meters long, 1.3 meters high beam, 1.26 meters wide roof, 0.45 meters wide floor, weight 36.09 tons.

In order to ensure the smooth erection of the first prefabricated beam of the tailwater platform of the plant, the project department formulated the construction plan scientifically, held a special construction seminar in advance, organized the on-site construction team to implement the technical information and operating procedures, optimized the equipment and manpower allocation, and strengthened the on-site construction organization. All the construction personnel were required to strictly follow the operating procedures during the erection process to ensure that all links were closely connected. Ensure the safety, quality and efficiency of erection construction, and provide a strong guarantee for the smooth erection of the first prefabricated beam of the tailwater platform of the plant. At present, the building construction of the dam project of Shaping I Hydropower Station is in the key sprint stage, and the successful erection of the first prefabricated beam of the tailwater platform of the plant has pressed the "acceleration key" for the construction of the plant. Next, the project department will continue to anchor the power generation target of the first unit, and under the premise of ensuring safety, go all out to ensure the completion of all work with quality and quantity, and steadily move forward to achieve the power generation target of the first unit on schedule.


】【打印繁体】【投稿】 【收藏】 【推荐】 【举报】 【评论】 【关闭】【返回顶部
今日热点