摘要:6月7日,记者从煤层气公司韩城采气管理区了解到,这个管理区深层煤岩气开发取得新突破,3口深层煤岩气高效建产试验井累计产气量超80万立方米,日产气量是其他同类气井的2倍以上,验证了深层煤岩气直丛井提产提速高效建产方案的可行性。这个管理区针对大吉气田河西深..

分享到:

6月7日,记者从煤层气公司韩城采气管理区了解到,这个管理区深层煤岩气开发取得新突破,3口深层煤岩气高效建产试验井累计产气量超80万立方米,日产气量是其他同类气井的2倍以上,验证了深层煤岩气直丛井提产提速高效建产方案的可行性。

这个管理区针对大吉气田河西深层煤岩气直丛井开发,持续在全生命周期高效建产上下功夫,以“剥洋葱”的方式逐一分析河西深层煤岩气直丛井压裂、试气资料,明确了施工总液量、总砂量、平均砂比、施工压力等九大高产主控因素,确定“地质条件是高产基础、改造程度是高产前提、储层保护是高产保障、地层能量是高产关键、控压生产是高产保证”5条高产井培育方式。

这个管理区严格落实地质工程一体化,合理利用地层天然能量,打破传统压裂投产方式,通过调整施工顺序、推行橇装化设计施工等措施,实施连续气举快速投产,精准把控生产节奏,有效避免压井、冲砂、钻塞导致的储层伤害,气井投产周期由35天缩短至12天。

On June 7, the reporter learned from the Hancheng gas production management area of coalbed methane Company that the development of deep coal and rock gas in this management area has made a new breakthrough, and the cumulative gas production of 3 deep coal and rock gas efficient production test Wells exceeds 800,000 cubic meters, and the daily gas production is more than 2 times that of other similar gas Wells, verifying the feasibility of the production and efficient construction of deep coal and rock gas straight cluster Wells.

Aiming at the development of Hexi deep coal and rock gas straight cluster well in Daji gas field, this management area continues to make efforts in the efficient production of the whole life cycle, analyzes the fracturing and gas test data of Hexi deep coal and rock gas straight cluster well in the way of "stripping Onions" one by one, and determines nine main controlling factors such as the total construction liquid volume, total sand volume, average sand ratio and construction pressure. The cultivation methods of 5 high production Wells were determined, which were "geological condition is the basis of high production, reconstruction degree is the premise of high production, reservoir protection is the guarantee of high production, formation energy is the key to high production, and controlled pressure production is the guarantee of high production".

This management area strictly implements the integration of geological engineering, rationally utilizes the natural energy of the formation, breaks the traditional fracturing production mode, and implements continuous gas lift rapid production by adjusting the construction sequence and implementing skid-mount design and construction measures, accurately controls the production rhythm, effectively avoids reservoir damage caused by well killing, sand washing, and drilling plug, and reduces the gas well production cycle from 35 days to 12 days.