新疆可克达拉热电联产项目1号机组定子吊装顺利就位
责任编辑:cnlng    浏览:164次    时间: 2024-04-22 10:57:09    | 来源:山西电建 作者:张任田慧   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:近日,中国能建山西电建总承包建设的新疆可克达拉热电联产项目1号机组定子吊装顺利就位,标志着项目汽轮机发电机组安装工作将全面展开,为实现机组投产发电目标奠定了坚实的基础。该项目位于新疆可克达拉市经济技术开发区城西工业园区,主要建设1台50兆瓦背压汽轮发..

分享到:

近日,中国能建山西电建总承包建设的新疆可克达拉热电联产项目1号机组定子吊装顺利就位,标志着项目汽轮机发电机组安装工作将全面展开,为实现机组投产发电目标奠定了坚实的基础。

该项目位于新疆可克达拉市经济技术开发区城西工业园区,主要建设1台50兆瓦背压汽轮发电机组、2×320吨/小时高温高压参数的循环流化床锅炉、公共辅机系统及配套管道、电气设施,同步建设烟气脱硫、脱硝设施及其配套的热力站。为保证定子顺利吊装就位,可克达拉项目部精心策划,多次组织讨论优化吊装方案,制定详细周密的安全控制措施,确保吊装顺利进行。项目建成后,可满足当地用电、汽、热及民生供暖要求,提升当地居民生活幸福感,促进地方经济高质量发展。

Recently, the stator hoisting of Unit 1 of Xinjiang Kekedala cogeneration Project, which is under the general contract of China Energy Construction Shanxi Power Construction, was successfully installed, marking that the installation of the turbine generator set of the project will be in full swing, laying a solid foundation for achieving the goal of putting the unit into production.

The project is located in Chengxi Industrial Park, Kekedala Economic and Technological Development Zone, Xinjiang. The main construction is a 50 MW back pressure turbine generator set, 2×320 tons/hour circulating fluidized bed boiler with high temperature and high pressure parameters, public auxiliary machinery system, supporting pipes and electrical facilities, and simultaneous construction of flue gas desulfurization and denitrification facilities and supporting heat stations. In order to ensure the smooth lifting of the stator in place, Kekdala project Department carefully planned, organized and discussed the optimization of the lifting plan for many times, and formulated detailed and thorough safety control measures to ensure the smooth lifting. After the completion of the project, it can meet the requirements of local electricity, steam, heat and people's livelihood heating, improve the happiness of life of local residents, and promote the high-quality development of local economy.



】【打印繁体】【投稿】 【收藏】 【推荐】 【举报】 【评论】 【关闭】【返回顶部