安徽芜湖LNG接收站项目全场桥架实现全线贯通
责任编辑:cnlng    浏览:1313次    时间: 2024-08-16 14:32:04    | 来源:淮河能源燃气集团有限责任公司   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:本次贯通的全场桥架共分仪表、电气、电信三个专业,其中仪表桥架11000米,电气桥架10000米,电信桥架3000米。淮河能源燃气集团有限责任公司储罐事业部掯住目标节点,倒排施工计划,精心组织施工,不断优化施工工序,克服汛期现场持续雨天、地下水丰富等不利因素,合..

分享到:

本次贯通的全场桥架共分仪表、电气、电信三个专业,其中仪表桥架11000米,电气桥架10000米,电信桥架3000米。

淮河能源燃气集团有限责任公司储罐事业部掯住目标节点,倒排施工计划,精心组织施工,不断优化施工工序,克服汛期现场持续雨天、地下水丰富等不利因素,合理利用有效作业时间,灵活调整施工侧重与布局,建立沟通协调平台,及时解决各项施工问题,全力确保现场作业有序推进,项目工程安全、进度、质量目标全面受控,最终实现全场桥架贯通。

下一步,淮河能源燃气集团有限责任公司储罐事业部将以更加昂扬的姿态投入到项目建设中,充分发挥四支党员先锋突击队作用,强化施工组织、优化资源配置、提高施工效率,确保各节点目标顺利达成。

The bridge is divided into three majors: instrumentation, electrical and telecommunications, of which the instrument bridge is 11,000 meters, the electrical bridge is 10,000 meters, and the telecommunications bridge is 3,000 meters.

Huaihe Energy & Gas Group Co., LTD., Storage Tank Business department 掯 live in the target node, reverse the construction plan, carefully organize the construction, and constantly optimize the construction process, overcome the adverse factors such as continuous rainy day and abundant groundwater in flood season, rationally use the effective working time, flexibly adjust the construction focus and layout, establish a communication and coordination platform, and solve various construction problems in time. To ensure the orderly progress of site operations, project safety, schedule and quality objectives are fully controlled, and finally the whole bridge is connected.

In the next step, the storage tank division of Huaihe Energy and Gas Group Co., Ltd. will be invested in the project construction with a more ambitious attitude, give full play to the role of the four vanguard commandos of party members, strengthen the construction organization, optimize the allocation of resources, improve the construction efficiency, and ensure that the node objectives are successfully achieved.