摘要:在施工区域内,有一条沿现状梅观高速主路两侧布设的次高压燃气管道,三次横穿项目施工区域,严重阻碍了项目民康路以北范围内的施工进展。为解决这一难题,需要对现状次高压燃气管道进行停气碰口迁改,在梅观高速西侧新建一条长度约560米新管道,将制约施工的东侧管道..
在施工区域内,有一条沿现状梅观高速主路两侧布设的次高压燃气管道,三次横穿项目施工区域,严重阻碍了项目民康路以北范围内的施工进展。为解决这一难题,需要对现状次高压燃气管道进行停气碰口迁改,在梅观高速西侧新建一条长度约560米新管道,将制约施工的东侧管道迁改至西侧。 作为深圳梅观高速项目施工线路中的关键一环,开工以来,项目部便把次高压燃气管道改迁作为一个重要节点来抓,精心组织,科学施工,成立以项目负责人为组长的工作专班,与业主、设计、燃气产权等单位多次沟通对接,组织召开迁改协调会,使次高压燃气管道顺利完成碰口迁改。 接下来,深圳梅观高速项目部将继续严格落实各项管理举措,把牢安全质量,高标准推进剩余施工内容的建设,为实现“精品工程”的目标持续奋斗。 In the construction area, there is a sub-high pressure gas pipeline laid along both sides of the current main road of Meiguan Expressway, which crosses the construction area of the project three times, seriously hindering the construction progress in the north of Minkang Road of the project. In order to solve this problem, it is necessary to change the current sub-high pressure gas pipeline, build a new pipeline with a length of about 560 meters on the west side of Meiguan Expressway, and move the east pipeline that restricts the construction to the west side. As a key link in the construction line of Shenzhen Meiguan High-speed project, since the start of construction, the project department has taken the relocation of sub-high pressure gas pipelines as an important point, carefully organized and scientific construction, set up a special work team led by the project leader, communicated with the owners, designers, gas property rights and other units for many times, organized and held relocation coordination meetings. Make the sub-high pressure gas pipeline successfully complete the impact change. Next, Shenzhen Meiguan high-speed project Department will continue to strictly implement various management measures, secure the safety and quality, promote the construction of the remaining construction content with high standards, and continue to struggle to achieve the goal of "high-quality project". |