摘要:据悉,该冷却塔筒壁为现浇混凝土薄壳结构,塔筒支撑结构为44对人字柱,塔顶标高145米。自2024年1月20日开始环梁混凝土浇筑,至2024年7月1日,筒壁工程共历时163天,较计划工期缩短了100余天,共浇筑混凝土9400余立方米,为冷却塔整体竣工打下坚实基础。自2号冷却塔下..
据悉,该冷却塔筒壁为现浇混凝土薄壳结构,塔筒支撑结构为44对人字柱,塔顶标高145米。自2024年1月20日开始环梁混凝土浇筑,至2024年7月1日,筒壁工程共历时163天,较计划工期缩短了100余天,共浇筑混凝土9400余立方米,为冷却塔整体竣工打下坚实基础。 自2号冷却塔下环梁浇筑以来,织金清洁能源公司科学组织,精细施工,切实将安全质量放在首位,严格执行网格化责任制管理,层层验收把关,紧盯项目工期节点,系统盘点工程进度,科学规划施工工序,确保工程建设有序推进。 2号冷却塔的顺利结顶,为后续冷却塔淋水构件安装创造了有利条件。下一步,织金清洁能源公司将持续发力,全力推进后续的淋水构件吊装,确保2号冷却塔年内具备通水条件。 It is reported that the wall of the cooling tower is a thin shell structure of cast-in-place concrete, the support structure of the tower is 44 pairs of herringbone columns, and the top elevation of the tower is 145 meters. Since the concrete pouring of the ring beam began on January 20, 2024, to July 1, 2024, the construction of the cylinder wall lasted 163 days, more than 100 days shorter than the planned construction period, and a total of more than 9,400 cubic meters of concrete was poured, laying a solid foundation for the overall completion of the cooling tower. Since the pouring of the ring beam under the No. 2 cooling tower, Zhijin Clean Energy Company has scientifically organized, fine construction, effectively put safety and quality in the first place, strictly implemented the grid responsibility system management, layers of acceptance check, closely focused on the project period node, systematic inventory of the project progress, scientific planning of the construction process, to ensure the orderly progress of project construction. The smooth topping of No. 2 cooling tower creates favorable conditions for the installation of subsequent cooling tower spray components. In the next step, Zhijin Clean Energy Company will continue to make efforts to promote the subsequent lifting of water sprinkling components to ensure that the No. 2 cooling tower has water conditions within the year. |