摘要:4月30日,新会区固废综合处理中心项目1#汽轮机一次冲转发电并网成功,标志着该项目顺利完成1号线工程建设任务,正式进入生产运行阶段。该项目位于广东省江门市新会区境内,项目生活垃圾总处理规模2250t/d,其中本期处理规模2×750t/d,预留二期处理规模1×750t/d。本..

分享到:

4月30日,新会区固废综合处理中心项目1#汽轮机一次冲转发电并网成功,标志着该项目顺利完成1号线工程建设任务,正式进入生产运行阶段。

该项目位于广东省江门市新会区境内,项目生活垃圾总处理规模2250t/d,其中本期处理规模2×750t/d,预留二期处理规模1×750t/d。本期工程配置2台750t/d机械炉排焚烧炉,1台45MW的汽轮发电机组,余热锅炉选用高温超高压(485℃,13.5MPa),烟气净化采用“SNCR 炉内脱硝+半干法+干法+活性炭吸附+布袋式除尘器+SGH+SCR”的组合处理技术,建成后将实现江门市新会区生活垃圾“无害化、减量化、资源化”处理,进一步缓解当地环境污染压力,改善生态环境,实现经济与环境协调发展,对助力经济与社会发展具有重要意义。

该项目自开工以来,受江门市恶劣天气影响,工期十分紧张,劳动力及物资设备进场面临严峻考验。面对艰巨的目标任务,公司充分发挥自身项目管理优势,根据项目并网发电时间节点和施工进度要求,结合物资设备排产到货计划,合理调配物资设备和劳动力资源,实现了资源最优配置,确保了项目工程高质量稳步推进。

On April 30, the 1# steam turbine of Xinhui District Solid Waste Comprehensive Treatment Center project was successfully connected to the grid, marking that the project successfully completed the construction task of Line 1 and officially entered the production and operation stage.

The project is located in Xinhui District, Jiangmen City, Guangdong Province. The total domestic waste treatment scale of the project is 2250t/d, of which the current treatment scale is 2×750t/d, and the second phase treatment scale is 1×750t/d. This project is equipped with two 750t/d mechanical furnace incinerators, one 45MW steam turbine generator set, the waste heat boiler uses high temperature and ultra-high pressure (485℃, 13.5MPa), and the flue gas purification adopts the combined treatment technology of "SNCR furnace denitration + semi-dry method + dry method + activated carbon adsorption + cloth bag dust collector +SGH+SCR". After completion, domestic waste in Xinhui District of Jiangmen City will be "harmless, reduced, and resource-based" treatment, which will further alleviate the pressure of local environmental pollution, improve the ecological environment, and realize the coordinated development of economy and environment, which is of great significance to boost economic and social development.

Since the project started, affected by the bad weather in Jiangmen City, the construction period is very tight, and the labor force and materials and equipment are facing a severe test. In the face of arduous goals and tasks, the company gave full play to its own project management advantages, according to the project grid-connected power generation time node and construction schedule requirements, combined with the material and equipment production and arrival plan, rationally allocated materials, equipment and labor resources, realized the optimal allocation of resources, and ensured the high-quality and steady progress of the project.